Updates & Progress

Wellness and Rehabilitation Institute: Construction Update, Week of July 21, 2014

Interior spaces are taking shape now as work progresses to walls and windows.  This week at the construction site: Brick installation continues along the east and west sides of the building. Interior partitions are almost completely framed in the new addition. Drywall is being hung in the east half of the addition. Electrical and mechanical […] Read story

Wellness and Rehabilitation Institute Construction Update: Week of June 23, 2014

This week at the construction site: Exterior wall framing continues. Structural steel frame is complete. Masonry wall construction is ongoing. Concrete floor slabs will be poured on the ground floor. Interior wall framing, duct installation and electrical rough in continues. » For a live view of construction any time, visit our web cam. » Learn […] Read story

Wellness and Rehabilitation Institute Construction Update: Week of June 16, 2014

This week at the construction site: Exterior wall framing continues. Air infiltration barrier is being applied. Exterior brick is being installed at the east end. Roofing of the new addition continues. More concrete floor will be placed. Interior partitions are being framed. Sheet metal duct work is being hung. » Web cam for a live […] Read story

Wellness and Rehabilitation Institute Construction Update: Week of June 9, 2014

This week at the construction site: The structural steel erection for the addition will be nearing completion. Exterior wall framing and sheathing continues. Roofing of the existing building is ongoing. Installation of the brick facade starts on the east end of the addition. » Web cam for a live view of construction any time. » […] Read story

Wellness and Rehabilitation Institute Construction Update: Week of June 2, 2014

Construction of the new Nazareth College Wellness and Rehabilitation Institute is moving along.  This week at the construction site: Interior demolition of the west end of Carroll Hall. Pouring of concrete slab at the east side of the addition. Framing of the exterior walls begins. Roofing work begins at the east end of the building. […] Read story