Wellness and Rehabilitation Institute: Construction Update, Week of September 8, 2014

                  With the exception of the west entry ramp and stair, the brick is nearly completed. Windows on the south elevation will be completed shortly. Installation of roofing materials begins. Installation of the new storm water system is underway. All the interior partitions are framed and most […] Read story

Wellness and Rehabilitation Institute: Construction Update, Week of August 18, 2014

This week at the construction site: Brick and window installation on the south elevation is nearly complete. Storm water systems will be constructed over the next few weeks on the east and south sides of the building. Interior partitions in the east half of the addition are almost complete. Hanging of drywall on the partitions […] Read story

Wellness and Rehabilitation Institute: Construction Update, Week of July 21, 2014

Interior spaces are taking shape now as work progresses to walls and windows.  This week at the construction site: Brick installation continues along the east and west sides of the building. Interior partitions are almost completely framed in the new addition. Drywall is being hung in the east half of the addition. Electrical and mechanical […] Read story

Wellness and Rehabilitation Institute Construction Update: Week of June 23, 2014

This week at the construction site: Exterior wall framing continues. Structural steel frame is complete. Masonry wall construction is ongoing. Concrete floor slabs will be poured on the ground floor. Interior wall framing, duct installation and electrical rough in continues. » For a live view of construction any time, visit our web cam. » Learn […] Read story

Wellness and Rehabilitation Institute Construction Update: Week of June 16, 2014

This week at the construction site: Exterior wall framing continues. Air infiltration barrier is being applied. Exterior brick is being installed at the east end. Roofing of the new addition continues. More concrete floor will be placed. Interior partitions are being framed. Sheet metal duct work is being hung. » Web cam for a live […] Read story